ITANAGAR, Nov 09: Chairing a review meeting with the PWD (Highway Zone), MoRTH representatives and contractor T K Engineering here on Monday, Chief Minister Pema Khandu constituted a committee to monitor 24X7 progress of Package-A of NH-415 (from Chandranagar to Papu Nallah) and coordinate with implementing agency for completion of the project before March 2021.
While monitoring the progress daily, the panel headed by PWD (design & planning) Chief Engineer Atop Lego with to CM’s joint secretary Kangki Darang, OSD to CM Lham Tashi and consultant Pradeep Mehta as members, would coordinate with the contractor, liaise with other government agencies to remove hurdles, if any, to fast track the work, Khandu said.
Home Minister Bamang Felix and advisors to PWD Minister, Phosum Khimhun (EZ) and Phurpa Tsering (WZ) would also personally monitor work progress daily.
As pointed out by PWD (Highway Zone), Khandu urged T K Engineering CMD Rotu Techi to immediately overhaul his men and machinery deployed in construction of Chandranagar to Papu Nallah stretch.
He asked the CMD to immediately increase the number of labourers, bring in sufficient materials and deploy adequate tools and plants with the target in mind. He suggested the implementing party to plan a work-chart of 10-day each so that targets are achieved from the micro level.
“Don’t sit on your target of March 20, 2021. Plan and set a target of next 10 days to complete it. If you achieve the target set for the next 5 to 10 days, you will be able to complete the project even by February. Set February as the target and get down to work,” he said.
“Common people are suffering a lot. Therefore, we are not going to accept any excuses. Complete the stretch before March,” ordered the CM.
Felix said that the state machinery is fully committed to the project and ready round the clock for any kind of assistance to the contractors. He pointed that the ball was in the contractor’s court and if there’s any delay in completion of work, they will be the only one to blame.
“On behalf of the Home department, I assure you security and protection round the clock. In return, you just have to complete the project at hand by the deadline,” he committed.
Khimhun and Tsering too assured full cooperation and coordination with the contractors but demanded that progress should be seen on the ground immediately.
CMD Techi admitted that progress on the NH stretch suffered due to the pandemic and prolonged monsoon season. He, however, assured that except for the underpass and two bridges, rest of the work would be completed before the March 20 deadline.
While there was no shortage of materials, tools and plants, engaging labourers in good numbers has been a hurdle. He, however, informed that the issue is being resolved as now labourers are being brought in from states like Bihar, Jharkhand etc., he informed.
The 10.9-km (Package-A) stretch of NH-415 consists of two bridges, 36 culverts, one underpass, 9.83-km of protection walls and 17.025-km of side drains. While work on one of the bridges in Chandranagar is under progress, work on the other in the same area is yet to start.
Meanwhile, it was informed that the MoRTH has cleared all decks for the remaining stretch of Papu-Nallah to Banderdewa (Package-B and C) and the tendering process for Package-B is underway, to be followed by Package-C.
Status of several other projects under PWD was discussed in the meeting, also attended by the PWD commissioner, secretary and top engineers of Highway Zone. (CMO)