Four-lanning works of NH-415 in progress: SE

By A O News Service

ITANAGAR, Jan 30: The works of four-lanning of National Highway-415 has been progressing fast with a target for completion.

PWD (highway) superintending engineer Sumnyak Sumnyan along with EE Nani Tath and authorities engineer inspected the digging work of under pass at Bank Tinali here on Saturday to take stock of the progress and directed the engineers of M/s T K Engineering Consortium Pvt Ltd not compromise with work quality.

Except bridge and under pass, whose works started recently and would take around three months, carpeting and blacktopping to the NH is targeted to be completed by February end as the work progress in on course, the SE told this daily.

It is but natural for those who matter to accelerate the works as Chief Minister Pema Khand had threatened in September last that he would resign if four-lanning works are no complete by March 2021.

he project was started in Sept’ 2017 and was targeted to be completed by Sept’2020 but due to COVID-19 pandemic and long drawn out monsoon, the progress of work suffered.

The Itanagar–Banderdewa section of NH-415 (package–A) started in Sept’ 2017 and was targeted to be completed by Sept’ 2020 but due to COVID-19 pandemic and long drawn out monsoon, the work progress had suffered

However, despite all odds, the physical achievement was 72.46 % as reported on 01.09.2020 as informed during a  review meeting chaired by Chief Minister Khandu on September 3 last Highway department officers.

However, the PWD was directed to take up work on a mission mode and strictly adhere to the timeline as planned and targeted by them for early completion of the project while the work progress is reviewed every fortnight.