Pro-dam group demands cancellation of 142 MoUs with power developers

ITANAGAR, Apr 29: A pro-dam organization in the state has demanded the state government to cancel as many as 142 memorandums of understanding (MoUs) signed with various private power developers for execution of power projects.

Addressing reporters at Press Club here, Pro-Dam Movement of Arunachal Pradesh (PDMAP) pointed out that the companies so far have failed to commission any projects violating the terms and conditions of the agreements inked.

PDMAP president Taw Paul informed that the organization had submitted a memorandum to the Chief Minister on April 28 this year seeking termination of the MoUs besides, placing request for consideration of 13 other demands related to hydro power projects in the state.

Stating that a total Rs 1,495.73 crore was collected from various power developers (both public and private) as upfront money, the PDMAP sought a white paper from the government on the details of expenditure incurred on the projects.

It added that the state government should come clean on this and reveal to the public every detail of the expenditures incurred on the projects.

While the government continues to collect upfront costs in crores, the status of the projects on the ground speaks different, the organization alleged.

Paul also called for exploration of possibilities on making joint venture company with central PSUs and state agencies like Indo-Arun Hydro Power Coporation Ltd (IAHPC) so that both mega and micro hydro projects could be executed to create employment opportunities for the unemployed youths.

The organisation also sought a white paper on the revenue received from already commissioned hydro projects at the rate of 12 per cent.

The state government should bring into the public domain all the details about the investment and expenditure made from the revenue collected from the commissioned hydro projects, it added.

Pointing out that the government had in 2007 took a loan to the tune of Rs 225 crore from NHPC Ltd at 9 percent interest per annum to revive the sick Apex Bank, Paul said that the money had not returned in full to the PSU.

Alleging that illegal logging and deforestation activities are going on in Dollungmukh area in the name of submergence area of Lower Subansiri HEP, Paul said that illegal logging activities are done mostly outside the notified submergence area of the project thereby causing random loss of natural flora and fauna.

The organization has also sought clarity on total amount received by the state government towards Net Present Value (NPV), Compensatory Afforestation Fund Management and Planning Authority (CAMPA) from various power developers.

Meanwhile, seeking reservation of jobs for educated youths of the state in the power companies and projects, Paul said that as per the existing rules of the MoAs and MoUs signed with the various hydro developers, there is no reservation kept for Group A and B category of jobs.

“This a major setback for our indigenous educated youths.  Needful amendment in MoUs clauses should be incorporated for getting at least 40 percent job reservation in Group A and B category of job opportunity. There should be complete 100 percent reservation for the recruitment in Group C & D category of jobs while examination for same should be conducted under the supervision of the state government,” he added.