ITANAGAR, May 14: The power department has decided to go for phase-wise power shutdown from May 17 in several districts of the state for maintenance of electrical towers on the Pasighat-Roing 132 KV transmission line.
The first phase of shutdown would start from May 17 to 18 for 32 hours while the second from May 20 to 21 for 32 hours and the third from May 23 to 24 for another 32 hours, a power department communiqué informed here on Friday.
The proposed shutdowns have been approved by the NERPC Shillong, the communiqué said adding, if things go well as per plan depending upon improvement in weather condition and easy movement of man and materials to and from the site, the shutdown time may get substantially reduced.
During the shutdown period, the power supply to the affected districts would partially be maintained through Rupai-Namsai 33KV inter-state transmission line.
All district authorities had been requested to make appropriate contingency plans as per local condition and ensure that there is no power cuts to CCCs, DCH and Oxygen plants etc in their respective districts.
APSLDC on behalf of the state power department has expressed regrets for inconvenience and difficulties caused by the grid disruption due to the shutdown.
The department added that due to washing away of transmission tower No 213 on Pasighat-Roing 132 KV Transmission line last year, the power supply to eastern part of the sate from Pasighat has since been maintained through an ERS (Emergency Restoration System) erected at a safe distance from the original location.
The pile foundation for tower No 213 and 212 were started last year and were in good progress till out-break of the second wave of Covid-19 this year.
With the onset of monsoon, the ERS erected last year has become severely endangered by erosion caused by Dotung River near Loklung Village in Lower Dibang Valley about 8 km from Gadum Tinali, the last village of East Siang. The Power Grid Corporation Ltd has erected another ERS at a safe distance from the river Bank.
The Power Grid has asked for six days continuous shutdown for shifting the conductors from endangered ERS to new ERS and requested the North Eastern Power Committee (NERPC) Shillong, and Arunachal Pradesh State Load Dispatch Centre (APSLDC) for necessary approval.
Taking into consideration the urgent requirement of shifting the conductor to prevent a bigger problem of possible permanent damages to adjacent towers, and the outcome of the consultations taken by the power department with all the stake holders, the proposed shut down was finalised, the communiqué added.