RAGA, Jul 14: Kamle district Deputy Commissioner Adong Pertin on Wednesday reviewed the status of material arrangement for restoration of Tamen Bailey suspension bridge.
The highway division executive engineer of Ziro stated that advance payment for materials have been made and the materials are expected to reach Tamen by July 20 along with the engineers and technicians for the restoration work. Executives of the Kolkata-based Bridge and Roof Company (India) Ltd (BRCIL) corroborated this information.
On June 26, the DC had a joint meeting with the highway department, officers from BRCIL and local leaders of the district in which six weeks’ time was given to the firm for procurement of materials and restoration of the Bailey bridge.
The DC, meanwhile, constituted a district-level inquiry committee (DLIC) headed by Raga ADC for probing the causes of the damages to the bridge.
According to the preliminary report of the DLIC, the bridge in the initial stage should have been designed for 40-45 tonnes capacity taking into consideration the TAH construction works. The panel found that the crossing of an overloaded dumper by one Pranob Jyoti Deori, driver and ex-worker of BRCIL now working with Bhartiya Infra Company Ltd, a highway construction company engaged in Package-III, was the main cause of damage to the bridge.
The DC directed the chairman of DLIC to submit the report to him without further delays. (DIPRO)