1050-metre escape tube opens
By Pradeep Kumar
ITANAGAR, July 30: The 1050-metre escape tube of one of the two tunnels of main Sela Tunnel was excavated open much ahead of schedule on July 22 last, Border Roads Organization (BRO)’s Project Vartak chief engineer Brig Harish Kumar told this daily over telephone on Friday.
The Sela Pass located at an altitude of 13,800-ft in Tawang district remains traffic unworthy round the year due to heavy snowfalls and fog. As the strategic Balipara-Chardur-Tawang road passing through Sela Pass is used by the armed forces for movement to the Indo-China border, the Defence Ministry had decided to develop the Sela Tunnel from national security point of view, he said.
Thus, Prime Minister Narendra Modi had laid the foundation stone of Sela Tunnel on 09.02.19 to provide all-weather connectivity to Tawang.

CE Brig Harish
Works of two planned tunnels – one 980-metre long and other 1555-metre long – have been progressing at fast space considering the sensitivity of the projects, he said, adding the construction had started on 01.04.19 with first blast on 31.10.19 to speed up pace of excavation.
BRO Director General Lt Gen Rajeev Chaudhary virtually conducted the last blast of escape tube of under-construction Sela Tunnel to facilitate its faster completion, he said.
Works on two planned tunnels at Sela Pass, one 980 meters long and other 1,555 meters, have been progressing at fast space considering the sensitivity of the project, Brig Kumar said, adding the DG BRO had conducted the first blast of the escape tube during his visit on Army Day in January last.
The tunnel is being excavated below Sela Pass on National Highway 13, part of Trans-Arunachal Highway, to offer a fair weather passage round-the-year and to reduce travel time from Tezpur in Assam to Tawang, he reasoned.
The BRO DG during his recent visit to Arunachal also had reviewed progress of Sela Tunnel works. Interestingly, the Sela Tunnel is being developed with new Austrian tunneling technology much below the snow line so that there is no need to remove snow during winter season.
The tunnel would be the longest in the world and would help speedy response of the soldiers in case of natural calamities besides their faster movement for deployment along the LAC, the Defence Ministry said earlier adding, it would facilitate speedy socio-economic development of entire North Eastern region, Arunachal Pradesh in particular.
This development comes at a time when standoff between India and China in eastern Ladakh has been continuing since May last year and Chinese President Xi Jinping’s recent visit to Nyangchi, a province-level city and Yarlung Tsangpo (known as Brahmaputra River in India) in Tibet, bordering Arunachal Pradesh. In fact, China in current 14th Five Year Plan has approved plans to build a massive dam on Yarlung Tsangpo, raising concerns among coastal states of India and Bangladesh. Meanwhile, His Holiness Dalai Lama has termed Chinese President Jinping’s visit to Tibet as a threat to India
China claims Arunachal Pradesh as part of South Tibet, which has been out rightly rejected by India. India and China share 3,488-km Line of Actual Control (LAC) which is marred by dispute.
It may be recalled that Union Home Minister Amit Shah while elaborating the country’s border policy recently has said that six tunnels have been successfully built on the country’s borders in the last six years.