“Siang River crossed its danger level today and water level is higher than last year. Its inflow at Tuting in Upper Siang district near China border has recorded 2.48m increase in flow level for which it would increase in downstream areas further,” Water resources department (WRD) EE Gonong Pertin said. “Today’s flow level has surpassed last year’s highest flow level of 154.29m by 16 cm by 5 PM for which soil erosion was caused at Jarkong, Sigar and Borguli areas under Mebo Sub-Division”, he added.
From Our Correspondent
PASIGHAT, Aug 26: The mighty Sing River with huge volume of water discharged by its tributaries Siyom, Simang, Yamne & Siku due to incessant rains since past several days has swollen up and flowing above danger level on Thursday.
This prompted East Siang district administration to alert people living in downstream not to venture in and around the Siang River for fishing and driftwood collection.
Siang River has started eroding on right and left banks, like Jarku and 21 mile area under Pasighat and Sigar, Old Borguli, New Borguli, Seram and Namsing villages under Mebo sub-division.
Large agricultural fields in the district have been inundated while road and gushing flood water damaged infrastructures in many parts of this district headquarters.
One member from each household – men, women & youth – of Jarku village despite heavy rainfall were seen voluntarily engaged in making boulder flood control bundhs along Siang River bank to minimize soil erosion.
Pasighat Municipal Council councillors Rebeka Panyang Megu (ward-4) and Okeng Tayeng (ward-8), busy supervising the flood control work today at Jarku, urged state Govt to grant fund for emergency flood control measures to stop further soil erosion.
Jarku residents Obang Taruk and Taying Darang said that they have been urging Pasighat WRD to supply more boulders for flood control works while Taying Darang said cement cube prepared by WRD is not that useful.
If flood erosion is not restricted on Jarku/Jarkong side, the advance landing ground, SS Mission area & Bering village would be in danger, senior citizen Obang Taruk said.
Moreover, the DA has also urged the public not to venture out in and around the Siang river bank for their safety.
DIPRO adds: Reports of large-scale damages of agriculture and horticulture fields, including bamboo groves have been pouring in.
The Bailey bridge at Suple village connecting six upstream villages has been washed away. The power channel and water conducting system of Subbung Hydropower Plant has been damaged due to landslide affecting power generation. Power transmission lines have also been destroyed at many locations. The Hydro Power Development department has informed that manpower would be deployed at the earliest to clear the channel.
Approximately 550 persons have been evacuated from GREF labour camps in the area to a temporary relief camp at Boleng Govt HS School. Repair, reconstruction and maintenance work is already underway in sites that were damaged earlier in the months of June and July.
Pangin-Boleng MLA Ojing Tasing has been in constant touch with the DA to ensure immediate restoration of essential services and communication lines while DC Atul Tayeng informed that the ongoing monsoon has caused severe destruction to Siang’s communication lines with unprecedented flooding of Simang River on Thursday. The MLA and the DA have instructed the departments concerned to assess the damages caused.