ITANAGAR, Aug 27:  Referring to Assam official notification of Dehing-Patkai National Park of 09.06.21, Wanglin Lowangdong during question hour on Friday said that those disputed lands are his ancestral property. Despite agreements to maintain status quo between two neighbouring districts, he questioned as to why Assam Govt has been trying the capture state land?

The GoAP is aware of the notification, Home Minister-cum-Border Affairs Minister Bamang Felix said, adding a high powered committee constituted on 15.07.21 to assess problems of 12 border districts had three sittings. The district level committees would submit their reports within two months for the reality to surface, he said.

Pointing out that Assam has been sticking to 1951 boundary notification to capture state lands; Ering suggested moving the Supreme Court. The GoAP would appeal to the apex court, where the case has been pending since long, Felix said.

Recruitment: Responding to supplementary from Jikke Tako on appointment of non-teaching staff in Tali circle of ISSE, Education Minister Taba Tedir said that there is no direct recruitment as it is done through departmental promotion committee.

Illegal appointments: Raising a supplementary, Ering lauded Minister Tedir for instituting inquiry against illegal appointments. Terming East Siang district case as tip of the iceberg, he said that let thousands criminals go unpunished but not a single innocent be punished, but pleaded to hand over the case to SIT. However, Tedir said the inquiry report was startling and action has been initiated. But actions would be taken based on final report of the probe, he assured.

TAH: On physical achievement 324-km from Nechipu to Hoj of Trans-Arunachal Highway (TAH), former CM Nabam Tuki asked how the rest portion would be built with low fund allocation? Many roads, particularly Kalajan to Hoj, have been damaged and how much funds allocated to PWD for maintenance, he asked?

CM Khandu, holding PWD portfolio, said that 2,300-km TAH has been given to PWD (978-km), NHID (753-km), MoRTH (324-km) and BRO (325-km) for execution. As only 20% of estimated maintenance cost is only given by MoRTH, the matter was taken up with Union Law & Justice Minister Kiren Rijiju here recently as Arunachal cannot be treated like other states. Thus, Rijiju has been holding meeting with officers concerned. On receipt of funds, the damaged roads would be renovated by calling tenders, he added.

The Naharlgaun-Banderdewa road is dilapidated too and its maintenance would be taken up with the MoRTH, the CM said.

 Smart City: On Itanagar Smart City (ISC), Techi Kaso advocated finding solution to land requirements through discussion. But he asked the status of Rs 1,000 crore granted by the Centre for ISC,?

In response, UD Minister Kamlung Mossang said that the estimated cost of ISC was Rs 1,298.76 crore. However, tenders worth Rs 190 crore were floated after forming an advisory committee, but the Centre had released only Rs 151 crore and Rs 83 crore utilized so far, he informed.

Fire station: In a supplementary, Tarin Dakpe said that many buildings were damaged during constructing of fire station at Raga in Kamle district but why it is not complete as yet?

HM Felix said that a fire station involves manpower, properties and funds, which is in freeze now due to austerity measure. It would be taken up only after lifting austerity measure, he assured.

Highlighting that Dirang records frequent fire mishaps, including the daily market was also gutted, Phurfa Tsering asked why a fire station at Dirang is yet to materialize despite assurance by two CM?

Terming fire mishaps a major problem in the state, HM Felix assured to assess where fire station would be needed across the state and Dirang case would considered on availability of fund.

Mutchu Mithi informed that Roing fire station building is of 1960s which should be rebuilt or else it would get burnt itself.

Water project: When Tanpho Wangnaw wanted to know reasons for delay in completion of water supply project of Longding town, PHE&WS Minister Wangki Lowang said that many factors caused delay, including local and insurgency problems. But the project would be completed by March next, he added.

Thirty questions including 20 starred were enlisted for the day while Biyurm Waghe, Rode Bui, Phosum Khimhun & Tapuk Taku were named as panel of chairmen for the session.

Besides enlisted business including presentation of CAG report of 2019, CM Khandu introduced The Arunachal Pradesh (Re-organisation of Districts) (Amendment) Bill, 2021. The statement and objects of the bill reads: “shifting of Kra-Daadi district HQs from Jamin to Palin as it is centrally located”.

Informing that Lok Sabha Speaker Om Birla during his visit to Shillong in February last had urged all legislators to make best use of Parliament e-library, a store house of database since 1958, including pictures, e-magazines and all documents related to the Parliament, Dy Speaker Pongte reiterated the plea to all members as that would broaden their knowledge in democratic set up of this nation before adjourning the house for the day.