Meet PMGSY deadline of March 2022: DC

AALO, Dec 13: West Siang deputy commissioner Penga Tato, chairing a divisional level review meeting to take stock of all ongoing PMGSY roads phase-I and II here on Monday, exhorted all engineers and contractors to keep pace with all ongoing works as budgetary grants by the Centre would be frozen by March 31,2022 being fresh deadline of RWD.

He reminded all contractors of their assurance to maintain quality as per DPC and asked executing agency to supervise their works without leaving to the mercy of contractors. Failure on the part of contractors will not only give bad name to the district but result in blacklisting of the firm and deprive rural people of connectivity.

He called for speed up works on war-footing within remaining four months and hinted visiting all work sites within a week to take stock of the progress.

The contractors and executing agency have to work with commitment keeping in view of the given deadline to offer connectivity to unconnected rural areas, ZPC Babom Romin said.

RWD EE Jumnya Angu highlighted the objective of the meeting while AE Nyomar Karbak informed that lone 9-km PMGSY from Nyomdir to Beye at Aalo, sanctioned in 2017, was left incomplete defunct by a construction agency. New local contractor Idak Bagra has assured to complete it within six months.

Er Monga Yomgam spoke about 10.92-km Darak to Boru Raksap, 10-km Liromoba to Rise Roa, 31-km Pidi Rime to Gadi Mesi, 12.96-km Yomcha to Belo Road, 9.6-km Darak to Larmuk Potom, 38-m BUG Bridge Darak-Boru Raksap, Tabasora-Kadayi BUG Bridge and 5.70-km Pidi Rime to Tego Gamlin.

Slow progress of works in few PMGSY road works was observed and contractors were asked to expedite the process for which they gave assurance.

District planning officer Marjum Karga, ASW Gamnya Bagra & divisional accountant Jhummi Kamum also spoke. (DIPRO)