From Our Correspondent
PASIGHAT, Mar 25: The 2,880-MW (12×240 MW Dibang Multipurpose Hydropower Project, being built by National Hydro-Electric Power Corporation (NHPC) Ltd would affect downstream residents of Meka, Kangkong, Dambuk & Paglam blocks of Lower Dibang Valley and Monggu Banggo block of Mebo of East Siang district, who, however, and its residents gave go ahead signal to proposed 278-metre-high dam.
The Dibang Hydropower Project Downstream Area Affected Committee (DHPDAAC) led by chairman Gotem Tayeng, during its awareness-cum-fifth general meeting on Thursday at Borguli village of East Siang district attended by gaon murahs, PRI leaders, retired Govt officers and villagers, after threadbare discussion of all issues, said that the proposed 288-metre-high dam would benefit downstream population by controlling annual flood fury.
Moreover, it would generate 11,223 million units (MU) of energy to yield economic benefits to benefit for people of both states. The concrete gravity dam axis is located around 1.54-km upstream of confluence of Ashu Pani River and Dibang River would not pose any threat.
The committee demands included construction of guide strong protection wall along both river bank from project site intake point to Arunachal-Assam boundary; reservation of 60% group C and D posts for downstream affected people and extending help to downstream affected villages under corporate social responsibility schemes. The committee also urged the Govt and NHPC authorities to channelize dam water for irrigation of both sides Dibang River residents.
AONS adds: The foundation stone for the dam was laid on 31.01.08 by Prime Minister Hanmohan Singh and its construction is yet to begin. In 2013, Union Ministry of Environment and Forest rejected the project’s application of NHPC but works resubmitted it 2014. The dam has also been under intense local and international opposition to its tentative negative environmental impacts and forced relocations of Idu Mishmi tribal peoples. However, PM Narendra Modi Govt gave a renewed go-ahead for the project in 2019, for it intends to control flood and generate electricity. As of 2020, work was not progressing on either of two major dam in Assam region, Arunachal’s Dibang Valley and Lower Subansiri districts.
On completion, Arunachal Pradesh Govt will get 12% free power from the project, 1% free power for local area development fund (LADF). The total value of benefit to Arunachal to get from free power and contribution to LADF will be Rs 26,785 crore over the project life of 40 years.