Construction of Modern Abattoir House in Capital | Phassang pleads union minister to re-consider refund of grants

ITANAGAR, Mar 25: A team of Itanagar Municipal Corporation (IMC) led by Mayor Tame Phassang called on union minister for Food Processing Industries Pashupati Kumar Paras in New Delhi on Friday and submitted a representation appealing for waiving, re-consideration for refund of grants to Rs 305.943 lakhs with interest accrued to the tune of ten per cent per annum for setting up of Modern Abattoir House here.

During the meeting, the Mayor apprised the minister that the proposal for setting up of the Modern Abattoir House, was initially initiated by the state urban development & housing department and the same was submitted on April 25, to the ministry.

However, on the creation of the Itanagar Municipal Council (IMC), the subject matters were transferred to the corporation, he added.

Phassang further informed that the work was awarded on a turnkey basis to M/s Micro Transmission System, a Noida-based company on July 1, 2015.

While the execution of work started at Jullang village but the public had strongly agitated against the construction, stating that such project may badly affect the health and hygiene of the area.

As a result, the site had to be abandoned and later on with the intervention of the state government and request made to the Ministry of Food Processing Industries (MoFPI) on July 6, 2017 and accorded approval for shifting of the site from Jullang to Chimpu area, he said.

“The date of completion of the project was fixed on June 15, 2019 and accordingly the work at the new site was started on June 6, 2017 after long delay,” Phassang informed.

He elaborated that as on date, 70 per cent of the work have already been completed on the ground while remaining 30 per cent are procurement of machinery and installation part.

“Machinery has already been booked at the OEM as DPR. Moreover, on the release of the next installment, the transportation, installation and other logistic works will be completed,” he added.

One of the major setbacks in the case was the central share of Rs 305.18 lakhs released on March 27, 2018 which, was directly deposited in the IMC escrow account instead of the state exchequer bypassing the norms and thus, causing a delay in the release of state’s share.

During the course of the technical hindrances, the country had suffered huge financial loss due to the Covid-19 pandemic and the state government was not exceptional. As such, the government was not in a position to allocate any fund provision for any ongoing project in the state.

“We appealed to waive the proposal of refunding and retrieving of project cost and re-consider any financial extension or as the case may be for one-time relaxation into the matter for successful completion of the project,” Phassang said.

Responding to the representation of IMC, the minister assured to look after the matter and ensured to visit Arunachal in August next.