4-lane phase-B construction gets new thrust

By Pradeep Kumar

NAHARLAGUN, Mar 27: While conversion of NH-415 from double-lane to four-lane is an ambitious project of present government to give much desired relief to the regular commuters, particularly office goers shuttling between Naharlagun and Itanagar, especially after completion of Package-A from Chandannagar to Nallah Papu Nallah tri-junction.

The 10-km Chandannagar-Papu Nallah tri-junction four-lanning with total 36 culverts was completed by 27th March 2021, according to PWD (highway) EE Nani That.

A  team armed with wood cutters and falkland, led by PWD (highway) junior engineer Debia Hania and his Power House electrical counterpart Tana Tokur Tara was busy in felling down tall trees at the entrance of this town after crossing the Barpani Bridge.

The work continued since 8.30 am till 2 pm Sunday that too without disturbing usual heavy vehicular traffic flow reflecting well chalked out strategies of both engineers and contractor Techi Naga. They were assisted by staff of power house (19), forest department (2) and and a dozen police personnel.

This area was originally Hornbill Park during North East Frontier Agency days, an elderly person said.

The works would continue to topple other trees from the proposed NH-415 fouor-lane area followed by shifting of public utility services, like electric poles and water supply pipes besides construction of drainage system, before beginning expansion of NH-415, they added.

The four-lanning of 52.4-km of Itanagar-Banderdewa section of NH-415 worth Rs 1,139.12 crore was sanctioned by Union Ministry of Road Transport and Highways on 07.04.21.

It may be recalled that Chief Minister Pema Khandu along with highway construction agency and other officials on 17.09.21 had inspected the proposed construction of four-lane of NH-415 from Naharlagun to Banderdewa (Package B and C).

The tender of 11.3-km of Naharlagun to Nirjuli (Package-B) had been completed, Khandu had said, adding the appointed date of work will be issued by the DC concerned after the completion of land acquisition.

On Package-C from 7.3-km Nirjuli to Banderdewa, he had said that a viaduct of around 1.1-km would also be constructed. The land acquisition of Package-C has been completed and the appointed date has also been provided to the contractor. So, The construction work of the said stretch hopefully would commence soon, he had said.

However, CM Khandu had appealed to Naharlagun and Banderdewa public of to bear with the inconvenience and cooperate with the executing authorities to complete the work within its stipulated time frame of 3 years, as directed by Union MoRTH.