ITANAGAR, Apr 18: The All Pipu Gyawepurang Youth Welfare Association (APGYWA) has appealed the Rural Works Department to conduct a departmental enquiry into the low quality and untimely completion of PMGSY road from Attarang Singhi to Pipu circle in East Kameng district.
The association in a complaint letter to RWD Chief Engineer against M/s Kaushal Sharma, has appealed the department for early completion of 20 km PMGSY road from Pachi to Lochung village.
The union said that the stage-II of PMGSY road from Attarang Singhi to Pipu circle was supposed to be completed by the year 2019. However, till date the road is yet to be completed. Moreover, the black topping of the road is at the lowest level which is being executed without sufficient machinery.
The association alleged that the number of CC culverts alongside the road have been decreased to 43, which is actually 53 according to the work sanction order. The CC drainage and culverts are of the worst quality due to which there are huge cracks leading to damage of the road and water stagnation.
“The DC even inspected the road construction in the year 2021. Accordingly, the DC instructed the contractors and the executing department for quality work and early completion of the project, which have been neglected,” the union further alleged.
In the context to the PMGSY road from Pachi to Lochung village, the association claimed that the executing firm M/s Kaushal Sharma has withdrawn almost a major chunk of the bill amount without completing the work.
Despite assurance by the district administration to look into the matter, it has failed to address the grievances of the villagers. The union also submitted repeated complaints and representation on the matter to the DC earlier.