Raja flags lack of suitable mechanism for inter-departmental coordination

ITANAGAR, Apr 29: In its efforts to optimise power generation from the state-owned micro, mini and small hydel plants operated and maintained by the Hydropower Development department, Power and Hydropower Advisor Balo Raja on Saturday convened a coordination meeting with the officers.

The power commissioner, secretary, and all the chief engineers of both the departments besides other officials attended the meeting.

It was observed during the deliberations that due to the lack of a suitable mechanism for inter-departmental coordination, there seems to have been communication gaps causing co-ordinational inefficiencies between the two departments.

Raja, in his address, advocated for strong coordinated actions by both the departments, who are the main stakeholders in the power sector in the state.

“Unless it is done, the hydel stations would not be able to generate in its optimum capacities just for want of issues pertaining to transmission and distribution, grid connectivity etc. Only good coordination will make it possible to develop a system that syncs with one another,” he pointed out.

Raja urged the officials of both the departments to have close coordination for the larger interest of the state, as he pointed out that the generation of power from the state-owned hydel stations could minimise the financial burden on the state exchequer in terms of the purchase of power from outside the state.

He added that for want of proper coordination between the two departments, the people are the ultimate sufferers, which needs to be addressed immediately.

He also suggested the officials of both the departments adopt the spirit of Team Arunachal as envisioned by Chief Minister Pema Khandu and work in harmony with each other to deliver the services to the state and its people, for which they have been meant.

A project-wise analysis was made in the meeting by both the CEs of western and eastern zones of the HPDD highlighting the issues wherever the interventions of the counterparts from the power department are required for resolving the same.

In the case of Nuranang hydel project in Tawang district, it was observed that the power being generated from all the hydel plants within the district can well be injected into the state grid or local grid, as the case may be, with prior consent from the State Load Despatch Centre (SLDC).

Similarly, the power being generated from the eastern side namely Kamba, Sippi, Sirnyuk Hydel plants can also be connected to the state grid.

The SE (SO&PSC) informed that as per the regulations passed by the Arunachal Pradesh State Electricity Regulatory Commission, 5 MW and above the capacity of power can only be injected directly to the grid system. Other smaller generators can also be injected directly into the state grid provided; the local distribution is not in a position to consume locally.

He advocated for the creation of a local grid by synchronising all such small hydels at the local level, thereafter, the integrated local system can easily be connected to the state grid at a suitable place with little planning and communications with the SLDC.

He added that basic requirements for synchronising into state grid, some important issues must be in place; such as, amongst others, installation of ABT compliant energy meters (energy meter which could measure and record energy generated in 15 minutes time block round the clock in sync with the GPS) and a very reliable communications system integrated into SLDC system.

Further, the necessity of day-ahead scheduling of 15-minute time blocks by all generators shall be mandatory, else the state may pay a huge amount as a penalty under CERC DSM regulations which can adversely affect the state exchequer.

In order to understand the business of electricity under the regulatory regime, all stakeholders need to update themselves and volunteered to share their experiences if asked. To mitigate all field level issues and operational gaps, he informed that the SLDC AP will start conducting quarterly state operational coordination meetings from this year onwards.

The SE (Transmission) has suggested for early transfer of all 33 KV HT and allied infrastructures to the transmission utility so that the issue related to grid connectivity could be made easier without elongating the due process while taking reference to Kamba hydel project.

The power commissioner had directed all the concerned SEs of hydropower and power departments to discuss the technical issues related to grid connectivity to all the projects, especially of Kameng and Siang basins with the SE (SO&PSC) on May 6 and sort out the problems.

He also directed them to submit its outcome to the government within a fortnight and admired the roles of CE (Commercial), SE (SO&PSC) and EE (SLDC) in enhancing the revenue generation with their all-out efforts in timely and real-time scheduling of available power for sale, which he informed that revenues to the tune of ₹231.75 and ₹309.48 crores have been earned by the state in 2020-21 and 2021-22 respectively.

Hydropower secretary in his deliberations also agreed to the views of the CE (Transmission) and suggested the DHPD officials have proper coordination with the power department right from the conceptual stage of any project so that the connectivity issues which are being surfaced now can well be avoided and deliver the benefits to the people instantly.

He also suggested coordination meetings by the departments on a regular or quarterly basis for the interest of the state.