By staff Reporter
BOLENG, Jun 21: The Border Road Organisation (BRO) road between Pangin – Boleng in Siang district has been disrupted since last Friday due to massive landslides.
The landslide occurred at 7 km away from Boleng. However, BRO has pressed its men and machineries to restore surface communication.
As boulders are falling continuously at block point, it would take more than 4-5 days to fully restore the road for vehicular movement, informed BRO officials.
As of now commuters are routing from Boleng-Geku-Yingkiong-Mariyang-Pasighat stretches.