Work on Greenfield Airport completed: Naik

ITANAGAR, Aug 10: Work on the Greenfield Airport at Hollongi near here, undertaken by the Airports Authority of India (AAI), was completed with test landing of aircraft and conduct of flight calibrations last month.

Various regulatory authority inspections have also been completed, state Civil Aviation Secretary Swapnil Mahesh Naik said in a communiqué on Wednesday.

The state Cabinet recently approved the name of the airport as Donyi Polo Airport.

The project was sanctioned by the Centre on January 18, 2019, under the Capital Air Connectivity Scheme as part of the PM’s special package on infrastructure development in the NE states.

The major civil constructions have been achieved within target, officials said. AAI has completed Package-I (runway and pavement work) and Package-II (construction of the interim terminal building).

“According to the standard guidelines, AAI has organised various regulatory authority inspections and has successfully conducted flight calibrations and test landing of aircraft from July 19 to 21 last besides, inspection by Director General Civil Aviation officials.

The Bureau of Civil Aviation Security also conducted an inspection of the airport on August 4, the communiqué said.

According to the procedure, after detailed inspections, observations made by these regulatory bodies are being complied with by AAI and the state government. It is being ensured that the airport would be ready for operations with all the safety measures in place.

Meanwhile, the state government has approached various airline operators for the introduction of scheduled commercial flights from the airport to the rest of the country at the earliest, the communiqué added.