October ’22 deadline to finish Miao-Vijoynagar road : DyCM

ITANAGAR, Sept 06: “October 2022 has been fixed as deadline for completion of Miao-Vijoynagar PMGSY road,” said Deputy Chief Minister Chowna Mein, in his presidential address to a meeting to review status of the strategic road here on Tuesday.

Though the road was sanctioned in five parts, but part-I (12.50-km), part-II (14.50-km) and part-III (34-km) works have been completed, while the  length of part-IV (80-km Mazgaon to Gandhigram) after realignment  has been reduced to 66-km and part-V (16.56-km Gandhigram to Vijaynagar) and last phases would also be completed by October next, he said and assured all possible support of the state Govt and  called upon the executing agencies and the contractors to expedite the work by using all resources to make it ready by November 2022.

Difficult terrains coupled with landslides at several locations, marshy lands, unfavourable climatic causes for the delay.

RWD Minister Honchun Ngandam and local MLA-cum-UD, Food & Civil Supplies Minister Kamlung Mosang, principal secretary (finance( Dr. Sharat Chauhan, secretaries Y.W.Ringu (finance) & N.T.Glow (RWD), technical advisor K.C. Dhimole, PMGSY CE D.Nyodu, additional secretary (planning) R. K. Sharma and planning  director Pallab Dey were present while planning commissioner Prashant Lokhande, Changlang DC Sunny Singh and Changlang RWD EE Nyamar Rike attended virtually.   (PRO)

Related posts