Flood partially damages Lower Subansiri power project’s dam

By A O News Service

ITANAGAR, Sep 25: A guard wall at the powerhouse of NHPC’s 2,000 MW Lower Subansiri hydro project along Assam-Arunachal border, collapsed due to rising water level of Subansiri river, officials said on Sunday.

The incident took place on Saturday late night due to overflowing of the Subansiri river and the company has evacuated all its workers from the power house, where all the machineries are located, the officials said.

“Heavy rainfall in the foothills of Arunachal Pradesh increased water volume at the project. As a consequence, a portion of the guard wall of the power house collapsed,” he added.

An employee of NHPC said on condition of anonymity that the damage is recognised as a threat to the ongoing last phase of construction work of the power house, which is almost ready.

On Friday, one of the diversion tunnels at the project got damaged due to landslides. No person was injured in the incident, a senior official said.

According to NHPC Consultant A N Mohammed, the landslides at the tunnel had no effect on the main Subansiri project.

“The cavity above the diversion tunnel no 2 is being filled up and stabilised though the works are being hampered due to rainfall in the project area during the last few days,” he said in a statement.

The company had constructed five diversion tunnels as temporary measures to divert the river for construction of the dam foundation.

However, two diversion tunnels, tunnel no 5 was blocked in the outlet during 2020 and tunnel no 2 was blocked near the entry point on September 16 this year due to landslides.

“As the dam construction is nearing completion with 88 per cent progress, the necessity of the diversion tunnels is over and NHPC is planning to plug all the diversion tunnels after this monsoon,” Mohammed said.

In June, a person was killed and another seriously injured when the roof of the Intact Tunnel no 2 collapsed.

The Assam government in March this year had informed the state Assembly that partial commissioning of the 2,000 MW project has been postponed further till August 2022. However, it is yet to start.

The company had earlier set a target of March 2022 for commissioning its biggest project, being constructed along the Assam-Arunachal Pradesh border.

In December 2020, the NHPC had said that the Subansiri Lower Hydro Electric Project would be commissioned by March 2022.

Construction work of the ambitious project at Gerukamukh was stalled from December 2011 to October 14, 2019 due to protests by locals and many groups fearing safety and downstream impact.

According to a company estimate in January 2020, the cost of the mega project, which was scheduled to be commissioned in December 2012, had escalated to around Rs 20,000 crore from the initial worth of Rs 6,285 crore.

The Centre had allocated a total Rs 11,000 crore as of December 2010 for construction of the dam.

The Subansiri Lower Hydro Electric Project is the biggest hydro-electric project undertaken in India so far and is a run-of-river project.

The protests were primarily led by Krishak Mukti Sangram Samiti (KMSS), All Assam Students’ Union (AASU) and Asom Jatiyatabadi Yuva Chhatra Parishad (AJYCP).