ITANAGAR, Sep 25: The 132 kV Ziro-Daporijo power transmission line will be shut down from September 26 to 29 next.
The transmission line will be shut down for new construction and stringing of conductor in relocated towers no 118, 120 and 141, said Shillong-based North East Regional Load Despatch Centre, executive director Nabarun Roy.
A Power department official on Sunday said the shutdown will be from 6 am to 6.30 pm from September 26 to 29.
Men and materials have been arranged and are ready at the site for the work, the official said.
Meanwhile, many places in West Siang district are reeling under darkness as strong winds and heavy rains in the last couple of days due to uprooting of trees damaging power supply cables.
According to sources, the power supply to Bagra, Darka and Kombo areas are likely to be restored by Monday.