Siang in high spate, East Siang rings alarm bell

PASIGHAT, Oct 11: The East Siang district administration has sounded an alert of deluge due to unprecedented rise of the water level of Siang river.

Taking stock of the situation, DC Tayi Taggu on Tuesday made several rounds of visit around the river banks and appealed to the people residing in low lying areas to refrain from venturing into the river and nearby water bodies to prevent any eventualities.

He, however, asked the people not to panic as the water resources and disaster management departments are keeping a vigil on the situation and any impending danger would be informed to the people in advance.

Taggu also directed the government officials not to leave the district headquarters and stay alert to deal with the situation.

WRD executive engineer Gonong Pertin informed that he has been in constant touch with the executive engineer of Dibrugarh based Central Water Commission (CWC) Abhijit Kasliwal, who is in charge of CWC Guaging Station for Siang river at Tuting, Yingkiong and Pasighat.

According to Pertin no abnormal water flow at upstream of Pasighat is noticed at the CWC gauging station so far. He further informed that on October 10 and 11, Pasighat town received highest rainfall breaking all records of last 25 years but in-spite of such heavy rainfall, the flow in the river was within safe level.

WRD staff members are assessing damage due to heavy rainfall of this week, he added.

District Disaster Management Officer (DDMO) Tsangpa Tashi informed that Pasighat recorded highest rainfall on October 10 and 11 at. 482 mm and 480 mm respectively adding that the river is still in rising mode but flowing bellow the danger mark.

The danger level is 153.96 while it was on Tuesday flowing at 152.12.

In view of continuous rainfall in the district, the SDRF teams are monitoring the situation closely by visiting all vulnerable areas under Pasighat township.

Highway executive engineer Dabe Perme informed that the Pasighat-Pangin section of NH-513 blocked at 64 km, Pasighat-Siger section blocked at 14.700 km, 15.100 km and 16.500 km. Several landslides were also reported along different locations of different NHs while men and machinaries were deployed.

Power executive engineer Tarik Mize informed that heavy downpour raised the Sille river which washed away the electric poles and other electrical accessories on 11 kv line linking Sille to 12 mile area, snapping power supply.

Incessant rainfall is hampering maintenance and repairing works, he added. (DIPRO)