KHONSA, Nov 13: Though work progress of Hukanjuri-Khonsa (NH-315A) and Longding-Tissa-Khonsa (NH-215) stretches is satisfactory to a some extent, but it needs a new thrust to use 3 to 4 month working period with unpredictable weather condition to avail 100% opportunity, said Borduria-Bogapani lawmaker Wanglin Lowang after a joint inspection
His comment came after a joint inspection of above stretches of highway on Sunday by him along with an official team led by Tirap DC Taro Mize, PWD (highway) EE Nani Tath,. DLRSO i/c Pik Tayom, COs Lim Modi (Borduria( & Dr. Ripi Doni (Longo), AE (highway) P.N. Khrimey, M/s. Bharatia Infra Ltd representatives Puna Hinda and Kaushal Sharma.
The joint inspection of highway is to ensure that the line departments and working agency meet specific time while maintaining work quality, Lowangdong said and urged district people to cooperate with working agencies for smooth and timely completion of works to boost communication.
Roads are roots of all round development of the country, the district in particular, DC Mize said and stressed on package “C”, which has been delayed due to continuous monsoon rains. He assured all possible help of district administration in the interest of district development.
Highlighting status of highway projects as on October 31, EE Tath praised the MLA for his initiative for joint inspection of important highway under Khonsa PWD division, besides lauded the DC for his constant cooperation.
Hukanjuri – Khonsa, (Pkg-A) NH-315A (Contractor- M/s. Bharatia Infra Ltd), 9km = 100 % completed. Landslide took place at Chainage 4.20 & 5.70 km reported to CE Highway.
Hukanjuri – Khonsa road (Pkg-B) NH-315A (Contractor :- M/s. Puna Hinda) 3.24 km = 100% completed. BC damaged at few stretches.
Hukanjuri-Khonsa road (Pkg-C) NH-315A (M/s. Kaushal Sharma) 14km = progress is as per schedule. Additional T&P to be mobilized.
Hukanjuri – Khonsa road, (Pkg-D) NH-315A 1.17km = 85.02% Balance work, Except DBM & BC work, Targeted to complete within 20.11.22.
Longding – Tissa- Khonsa Road, NH-215 (M/s. SKS Infra Pvt Ltd), 53.17%. Damages observed in Drain, B/Wall, WMM & DBM at few stretches.
While interacting with the joint inspection team at circuit house, Old Tupi Chief Langthiam Lowang praised Lowangdong for constant concern over development activities in his assembly constituency. He assured full cooperation of Tupi village to work agency for road construction.
Tupi people later urged the joint inspection team to keep provision for slab culvert in few portion of roads in village area to avoid continuous leakage of drainage water to the road. (DIPRO)