By Pradeep Kumar
SORENG, Mar 03: The 414-km Teesta River originates from Teesta Khangtse Glacier, west of Pahunri Mountain or Teesta Kangse glacier above 17,700 ft and flows southward through gorges and rapids in Sikkim Himalaya and West Bengal and subsequently enters Bangladesh through Rangpur division. In Bangladesh and merges with Brahmaputra before falling into Bay of Bengal. The river has turned into a money-spinner for Sikkim.
In 1984, the state experienced peak time power shortage of 331MW and decided to harness its huge hydropower potential. Teesta Canal Hydroelectric Project (I)(II) of nine generating units (valve type water-wheel generator with capacity of 7.5 MW each); unit I, II, III & IV of 33 MW capacity of each (132 MW); 3×170 MW Teesta-V, run of the river scheme with diurnal storage have already been commissioned.
The under construction run-of-river 500-MW Teesta-VI Hydropower Project (THP), being developed by NHPC subsidiary Lanco Teesta Hydro Power (LTHPL), is expected to be commissioned in March 2024 with an investment of $833m.
The THP is a part of six hydroelectric projects being developed on Teesta River. It is located near Subin Khore village in southern Sikkim. The THP is expected to provide 12% free power to Sikkim as royalty for first 15 years, which will be increased to 15% thereafter. The remaining power produced from the project will be saleable energy.
The Sikkim Govt had allotted the project to LTHPL, which was then owned by Lanco Group, under a build, own, operate and transfer (BOOT) basis, in 2005. The hydropower project was originally expected to be commissioned by May 2012. It was, however, delayed due to funding-related issues, obtaining a forest permit, poor geology and an earthquake in 2011, which blocked logistics and all ongoing work.
LTHPL ran into financial difficulties, following which the lender group led by ICICI Bank approached the National Company Law Tribunal (NCLT) over non-repayment of loan dues by the company. Insolvency proceedings were launched against LTHPL in April 2018.
NHPC was declared by NCLT as the winner of the bid for the project and was asked to pay Rs 8.77bn ($124m) to the financial creditors and Rs111.2m ($1.57m) to LTHPL’s operational creditors.
The THP will feature a reservoir with a storage capacity of 1.38 million cubic metres. The project will have two modified horseshoe-shaped headrace tunnels (HRTs) with a diameter of 9.8m and length of 13.75km and 13.63km, respectively. The equipment will also include two 16m-diameter surge shafts and four units of steel-lined pressure shafts with a diameter of 5.4m and lengths ranging between 151m and 198m.
The project’s underground powerhouse will have a length of 142.75m, a width of 18.5m and a height of 52.44m. It will feature four vertical-axis Francis turbine units with a rated capacity of 125MW each.
A 26.5m-high barrage is being built across the river, and five radial gates, with a width of 15m and height of 17.5m each, are being installed. Four circular-shaped penstocks, with a length of 30.5m and diameter of 4.5m each, are also being installed. The project involves the construction of four D-shaped tailrace tunnels (TRT). Each tunnel will measure 270m-long, 8.5m-wide and 7.5m-high.
A dedicated 220kv DC transmission line will be used to evacuate the power generated from the power project. It will be connected to the Power Grid Corporation of India (PGCIL), Rangpo substation, which is located approximately 12.5-km away from the power plant.
The THP is funded by NHPC through a debt-equity ratio of 70:30. The estimated investment in the project, including acquisition cost of LTHPL, is Rs 57.48bn ($833m), based on July 2018 price levels.
The civil works contract for the project was awarded to Patel Engineering, an infrastructure and construction services company based in India. The contractual scope includes diversion works as well as the construction of barrage and spillway, penstocks, surface powerhouse, intake, pothead yard and tail channel.
The contract for the foundation engineering and geotechnical works for the project was awarded to BAUER Engineering India, a subsidiary of BAUER Spezialtiefbau. The company is responsible for construction of an anchored pile wall, grout curtain along the upstream cofferdam and diaphragm wall on the upstream side of the barrage.
Gammon Engineers and Contractors, an Indian civil engineering construction company, was contracted for construction of the balance civil works package. The package covers the underground powerhouse and transformer cavern, parts of HRT-1 and HRT-2, pressure shafts, surge shafts, TRT, and related works.
Alstom Projects India was contracted to supply four units of 125MW Francis turbines and generators in July 2009. The company also supplied main inlet valves along with control and protection systems. Furthermore, the contractual scope included design, engineering, erection, testing and commissioning. The company was renamed GE Power India in August 2016, following GE’s acquisition of Alstom’s power and grid businesses.
Jaypee Associate was awarded a contract for lot one works, including civil works of barrage, desilting basins, intake, parts of HRT-1 and HRT-2, and other associated structures, in March 2020.