- BRO building tunnel to bypass Sela Pass
By A O News Service
ITANAGAR, Jan 19: The Sela Pass, located at an altitude of about 13,700 feet, the main route that connects Tawang to the rest of India, though remain usually covered in snow year-round, but being winter season witnessed heavy snowfall on Thursday that stranded group of tourists..
Nearby Jang police station received a distress call from a group of 10 tourists, including three women, who were stranded near Sela Pass due to heavy snowfall.
The tourists, who had travelled from outside in two vehicles, a Maruti Swift Dzire and a Kia Sonet, were rescued by a team led by SI Pema Wangchu of Jang PS, a senior PHQ officer told this daily on Friday.
The police drivers, with their experience, drove the vehicles to safety. In light of the recent heavy snowfall, all travellers and tourists are advised to avoid travelling through Sela Pass unless absolutely necessary.
If travel cannot be avoided, it is recommended to use chains instead of ropes, which do not last. Traveling after 2 pm is also discouraged as it gets dark and sever cold, the officer added.
Sela Pass is the second highest pass in India and one of the highest motorable passes in the world.
A tunnel is being excavated by the BRO below the 4,200-metre Sela Pass, which is often closed due to snowfall and landslides. Once complete, the tunnel will reduce the distance between Dirang and Tawang by 10-km and the travel time by an hour.
Despite challenges of extreme low temperature which affect manpower and machinery alike, the work on Sela Pass tunnel, is progressing at a fast pace, according to BRO sources.
The Sela pass tunnel, a strategic link is being expedited by the BRO to build the approach road to Sela Pass, the lining of the tunnel is nearing completion, with electrical and mechanical work inside the tunnel almost over.
Drill and blast technique for excavation as part of New Austrian Tunneling Method (NATM) is being used for its construction. On completion, this would be the longest bi-lane road tunnel in the world, at an altitude above 13,000 feet.
The two tunnels and the 9.075 km approach road is being constructed in the Sela formation on the boundary of West Kameng and Tawang districts.
The lengths of the tunnels and approach roads were subsequently changed based on site conditions. The current configuration of the project is that Tunnel-1 (T1) is now planned for 993 m length; it was previously 475 m and it is a single tube tunnel.

The Tunnel-2 (T2) is now 1,591 m, which was conceived to be 1,790 m — the T2 tunnel is a twin tube tunnel, with one main and one escape tube.
The main tubes of both T1 and T2 are 12 m wide with overhead clearance of 5.5 m. The escape tube with T2 is 7.26 m wide with an overhead clearance of 4 m, being constructed parallel to the main tunnel at a distance of 20 m and is connected with five cross passages, the sources added.
This project has been designed for traffic density of 3,000 petrol cars per day and 2,000 diesel trucks per day, with max speed of 80 kmph.
The tunnels are being provided with a state-of-the-art electromechanical system, including jet fan based longitudinal ventilation system, firefighting devices, CIE norms based illumination system and SCADA controlled monitoring systems.
The sanctioned cost for the project is Rs 687 crore including pre-construction cost of Rs 10 crore and four years maintenance cost of Rs 15.63 crore.
In 2010, Director General Military Operations proposed tunnels along important areas in the Eastern Theatre to provide all weather connectivity to the border areas, which would enhance operational capability as well as provide succour to the local population.
Eastern Command was asked to undertake the feasibility studies for tunnels at Sela, Bomdila and Nechiphu in Arunachal Pradesh.
Since Sela remained snowbound for about eight weeks in a year, being the highest pass on the axis, it was decided to take up work on Sela tunnel at the earliest.
The tunnel was to be built in a strategically acceptable time frame, to offer all weather connectivity to Tawang.
The foundation stone of Sela Tunnel was laid by Prime Minister Narendra Modi on 09.02.19 and BRO’s Project Vartak was entrusted to oversee the construction, which had begun on 01.04.19 with first blast taking place at Nuranang side Tunnel portal on 31.10.19. There was an initial delay in mobilization of resources due to the COVID-19 pandemic.