By A O News Service
ITANAGAR, Mar 06: Chief Minister Pema Khandu gave away cheques worth Rs 219.18 crore here on Tuesday as land compensation to 96 families of Shi Yomi district affected by construction of 700-MW Tato-II Hydroelectric Project (HEP) over Siyom River by North Eastern Electric Power Corporation Limited (NEEPCO).
While the project, being executed by NEEPCO, would offer opportunities to people of Shi Yomi district bordering China, the works on 240-MW Heo and 186-MW Tat-I HEPs would also commence this year
Mechukha MLA-cum-Legislative Assembly Speaker Pradesh Pasang Dorjee Sona, Shi Yomi DC Liyi Bagra and NEEPCO officials were present.
In view of recent concerns over safety of mega hydro projects, particularly in Arunachal Pradesh, the National Hydroelectric Power Corporation (NHPC) has issued a press release reassuring the public of safety measures in place. The statement comes amidst growing apprehensions following Glacial Lake Outburst Flood (GLOF) incident in Teesta Valley in October 2023.
Teesta Valley incident, characterized by a GLOF event originating from South Lhonak Lake, prompted a reevaluation of dam safety protocols. However, NHPC stated that the technical disparities between the Teesta Basin and their projects in Arunachal Pradesh.
The NHPC said that most glacial lakes in Subansiri, Siang and Dibang River catchments are located in distant Chinese territories with minimum threat of GLOF-induced floods to NHPC projects. Moreover, the topographic and catchment characteristics of this hilly state differ significantly from that of the Teesta Basin, reducing the risk of similar events.
This has been explained in details by Bharatendu Sharma in his article ‘Arunachal mega hydro projects safe’, published in March 6 edition of this daily.
It may be recalled here that the state Govt while prioritizing to generate green energy had signed memorandum of agreement (MoA) with four major CPSUs, namely National Hydroelectric Power Commission (NHPC), Satluj Jal Vidyut Nigam (SJVN), Tehri Hydro Development Corporation (THDCL) and NEEPCO to develop 13 hydroelectric projects (HEPs) in presence of Union Power, New and Renewable Energy Minister R K Singh.
Of the 13 HEPs, SJVN was allotted five projects in Dibang basin – 420-MW Amulin, 500-MW Emini, 400-MW Mihundon, 3097-MW Etalin and 680-MW Attunli; the NEEPCO was given 186-MW Tato-I, 700-MW Tato-II, 1000-MW Naying), 500-MW Hirong and 240- MW Heo in Siang basin.
The NHPC was given HEPs – 1800-MW Kamala and 2000-MW Subansiri Upper in Subansiri basin while THDCL would execute 1200-MW Kalai-II HEP in Lohit basin.
All these projects were allotted to private developers which failed to execute prompting the state Govt to scrap the MoAs to reallocate to the CPSUs.
These 13 HEPs to generate 13,000-MW of power would draw investment of Rs 1.4 lakh crore, Singh had said. However, after inspecting under construction 2000-MW Subansiri Lower HEP located along Assam-Arunachal Pradesh border, Singh reacting to concerns of environmentalist, had said “I went into all the details and I believe that by and large, the project is progressing as it should”.
Informing that efforts were on to tap available hydropower capacity of the country, the minister had saing: “Today, our hydro power capacity is 47,000 MW, which is 35% of our available hydro power potential. Developed countries, however, have utilized around 70%.”