ITANAGAR, July 18: Though ambitious National Highway-415 aimed at serving as main thoroughfare of Arunachal Pradesh twin capital cities of Naharalgun and Itanagar, but its Naharlagun-Nirjuli stretch is in a pitiable condition due to poor implementation of Packages B & C to make the stretch a nightmare for the commuters.
The development of NH-415 is funded by Union Ministry of Road Transport and Highways. The release of fund is usually delayed for failure to submit utilization certificate with proofs.
The Package-B meant to develop the four-lane highway’s 11.3-km Papunallah to Nirjuli and Package-C for 7.464-km Nirjuli-Banderdewa, but these stretches are marred with potholes and water logging with mud making travelling too challenging.
Even after three years, Package-B is yet to see light of the day and residents of Naharlagun, Nirjuli, Doimukh and Banderdewa are the worst sufferers.
It may be recalled her that Chief Minister Pema Khandu had initiated Package-A on mission mode to complete the four-lane NH-415 on time. But, Packages B and C are yet to give shape to the highway.
Though Package-A was implemented to build 10-km stretch from Chandranagar to Papu Nallah, but monsoon triggered incessant rainfall has also damaged that stretch.
The best example is CM Khandu on 01.10.20 had threatened to resign if Package-A, except bridges and Bank Tinali Underground Pass, was not completed by 31.03.21. Taking it as a challenge, engineers of PWD (Highway) and contractors had completed it on time to save the image of the CM.
When the next targets are Package B and C, the new Govt led by CM Khandu for third consecutive term, needs to saw tangible result, but has remained a mirage so far giving a bad impression to the outsiders visiting the state often.
It is worth recalling here that NH-415 when under the care of Border Road Organization (BRO) as NH-52 was well maintained. Thus, those who matter when incapable of doing justice should give a serious thought about handing over of NH-415 to the BRO or the NHIDCL in greater interest of state people.
On June 25 last, CM Khandu, while chairing a review meeting to assess damages caused to stretches of NH-415 and other areas affected by cloudburst of June 24, had expressed dissatisfaction over e slow progress of Papu Nallah-Nirjuli stretch. He had asked PWD (Highway) engineers to expedite the work without compromising on quality.
A massive cloudburst in Itanagar had caused landslides, floods, and disruptions on NH-415. The Disaster Management Department had reported flood-like conditions, prompting warnings and setting up of relief camps for the affected families.
Why not replicate Gohpur-Tezpur (NH-15)?
Moreover, PWD (Highway) should take a cue from NH-15 (Gohpur-Tezpur) in Assam and replicate it in the state. The quality of work is inferior in comparison to Assam or else the completed Papu Nallah-Itanagar stretch would not have been damaged at many places by rains.
It is high time for those who matter to wake up from their deep slumber and work with commitment to facilitate better surface communication in state capital.