By Pradeep Kumar
HOLLONGI, Jan 29: The under construction permanent terminal building of Donyi-Polo Airport here would be ready by May or June next, said a senior engineer of Delhi-based Universal Engineering Private Limited, engaged by the Airport Authority of India (AAI) to build the ambitious project.
Heavy equipments and large manpower have been deployed for timely execution of the project on priority considering the sensitive nature of the work, he told this editor here on Tuesday while supervising the ongoing technical works and said that the authorities of state Govt led by Chief Minister Pema Khandu have been constantly monitoring.
The present temporary terminal building of the airport would be handed over to Indian Air Force (AIF) to operate its aircrafts and fighter jets besides to be used for cargo aircrafts, he informed.
However, large number of passengers came out after Indigo’s daily flight from Delhi landed around 12.30 pm while equal number of passengers entered to board the outgoing flight. Indgio also operates a to and fro flight to Kolkata daily. But, Arunachal Chamber of Commerce of Industry (ACCI) has lodged a written complaint with Union Civil Aviation Ministry and AAI against exorbitant high fares of Indigo on both routes and sought operation by other airlines to end monopoly of Indigo.
This domestic airport, also known as Hollongi Airport, located 14-km away from state capital Itanagar, spread in over an area of 320 hectare land, was built by the AAI as the 16th airport of NE India. Its foundation stone was laid by Prime Minister Narendra Modi virtually on 09.02.19, construction had started on 15.12.20 and inaugurated on 19.11.22 with first flight of Indigo Airlines from Kolkata landing on 28.11.22.
It may be recalled here that though the GoAP in 2007 had chosen Banderdeva, situated 25-km from Itanagar, as a suitable location for the project and the then Union Home Minister Shivraj Patil had laid the foundation stone on 20.02.07, but the AAI technical committee had rejected the site and recommended Holongi as an alternative site for the project in 2011. AAI had recommended Hollongi on grounds of operational safety, lower costs of construction and ease of future expansion. The Hollongi site lay on flat ground, had better usability in poor weather and offered scope for easy construction and expansion. As the project was getting delayed, the PMO eventually stepped in to put an end to the dispute in July 2012, and the Hollongi site was finalised.
The airport has a single 2,300 metre runway oriented east–west in the first phase, to serve narrow-body aircraft and can be extended to 2,800 metres to land wide-body aircraft. The present airport apron measures 160 metres by 115 metres linked to the runway by two taxiways. It has night landing facilities and navigation facilities like DVOR and Instrumental Landing Systems (ILS).
As Arunachal Pradesh shares 1,129-km of total 3,488-km Indo-China border and China often claims this Indian state as its territory (South Tibet), the speedy expansion is in process to tackle any eventuality if posed by the neighbouring nation, which is known for its ‘dog-tailed foreign policy’.