- VVP not extended to Indo-Myanmar border: Natung
By Staff Reporter
ITANAGAR, Mar 10: Advisor to PHED and WS Pani Taram urged the GoAP to issue a fresh tender for Trans-Arunachal Highway (TAH) Package-B stretches from Naharlagun to Itanagar and flyover road bridge of Naharlagun during zero hours discussion of the assembly here on Monday.
There is no progress in the construction of the flyover bridge of Naharlagun and maintenance of road from Nirjuli to Naharlagun by the construction agency, said Taram. Commuters are opting for outskirts road to reach Itanagar from Nirjuli and Banderdewa due to dilapidated condition of said road, he added.
“The TAH, as per the agreement of construction agency and GoAP, is expected to be complete by 2025, but the work progress is hardly 40%,” Taram rued.
Chief Minister Pema Khandu intervened to add that TAH construction across the state has almost been completed, sans Package-B.
“We are concerned about the convenience of commuters,” Khandu said and asserted that the construction agency has recently assured to complete the said stretch by May 2026 and submitted a work plan to the GoAP.
“If the construction agency fails to meet the target, I would convince the GoI To terminate the agency, he said, adding that the department concerned has been directed to take over the maintenance work from the contractor.
“Union Ministry of Home AffairsI had launched Vibrant Villages Programme (VVP) for the Northern Border (Indo-Tibet) in 2023, and no official communication has been received for extension of the VVP to Indo-Myanmar border region,” said Home minister Mama Natung in response to a question from Nampong MLA Laisam Simai.
The MoHA has identified 455 villages on priority basis under VVP in the state, these villages spread across the 28 blocks of 11 districts in northern border of the state, he said.
On status of Assam-Arunachal Pradesh boundary asked by MLA Wanglin Lowangdong, Natung said that in pursuance of 01.06.22 notification, the GoAP has reconstituted six regional committees to assess and examine the status of the boundary dispute.
Arunachal has been consistently opposing 1951unilateral notification of state boundary, the GoAP’s proactive efforts have led to an MoU allowing adjustment of lands inhabited by Arunachal people within 3-km into Arunachal Pradesh, Natung informed.
Chief Minister Pema Khandu, who hold charge of PWD, in response to Congress MLA Kumar Waii’s question on provide road connectivity to uncovered villages of the state, said that GoAP has taken up the matter with Union Rural Development Ministry to reduce size of eligible population the habitation for maximum coverage of uncovered habitation under PMGSY-IV.
When Waii asked about GoAP policy for road connectivity to newly recognized villages, CM said that, the newly recognized villages once become part of the census would be taken up under PMGSY–IV for connectivity as per population criteria.
Deputy Chief Minister Chowna Mein later presented gender budget, supplementary demands for grants for 2024-25, statement on budgetary provision for Urban and Local Bodies, child budget and appropriation accounts for 2023 -24.