Villagers ink MoU with GoAP to allow pre-feasibility study of Siang project

By Maksam Tayeng

BOLENG, May 23:  Pangkang (Kumku) villagers under Riga circle of Siang district have signed a memorandum of understanding (MoU) with the GoAP on Friday to allow pre-feasibility study (PFS) of Siang Upper Multipurpose Project (SUMP) at Boleng.

The proposed 11,500-MW SUMP would involve construction of a 300-meter-high dam on Siang River, a major tributary of the Brahmaputra which on completion would be one of the largest hydroelectric projects in the world.

This is a major development as on completion the SUMP, strategiccally designed, would counter  China’s rapid construction of world’s largest hydropower project on Yarlung Tsangpo, the upstream of Siang River in upper ridges of Tibet. The SUMP is envisioned as a timely and critical initiative to mitigate potential downstream risks by sudden upstream discharges and floods besides  ensure year-round water flow  for agriculture, drinking and ecological balance in NE India.

Siang DC P.N. Thungon, on behalf of the GoAP, and Pangkang leaders Taba Tamut and Bakin Tali. On behalf of villagers, signed the MoU in presence of Panchayati Raj, State Transport and Cooperation Minister Ojing Tasing, Hydropower joint secretary Hage Lailang & CE Atek Miyu and state BJP general secretary Nalong Mize.

According to the MoU, a development package of Rs five crore for infrastructure improvement, health services and livelihood programs would be given in next three years, to be implemented by a newly formed village development committee (VDC), comprising of project-affected families for their benefits.

The MoU also guarantees future consultations with local stakeholders as the project progresses, reaffirming the GoAP’s commitment to inclusive planning and development keeping in view local priorities. The SUMP is not just a mere hydroelectric project as it would ensure economic empowerment of local community as a major source of clean and sustainable energy

“The villagers have shown incredible wisdom and maturity by cooperating with the GoAP. This is not only about power or water but harnessing the potential of River Siang as a collective prosperity,”, Thungon added.

However, there was report of clashes between villagers and security forces at Geku on Friday when security forces with a magistrate restricted the villagers from heading toward Beging, proposed survey site for the SUMP, to join in a sit-in protest led by the Siang Indigenous Farmers’ Forum (SIFF), which opposes the project saying that they have not consented as it threatens to submerge their land, they claim.

According to sources, several platoons of central armed police forces (CAPF) are deployed in several areas, including Beging, Geku, Jengging and district HQs of East Siang (Pasighat), Siang (Boleng) and Upper Siang (Yingkiong). According to the SIFF and Dibang Resistance, forerunners in opposing large scale hydropower projects, the paramilitary presence is meant to assist NHPC officials in carrying out a PFS. Drilling machinery has been installed at Beging, sparking widespread anger by dam anti-protagonists, they alleged.