YINGKIONG, Sept 14: Upper Siang DC Talo Jerang on Sunday conducted surprise inspection of ongoing strategically important Panggo-Jorging defense road, aimed at improving connectivity to the Line of Actual Control (LAC) under Migging circle.
This strategic defence road is crucial infrastructure aimed at enhancing border security and facilitate socio-economic development in this remote border region.
Panggo village, located 120-km from the district HQs here, is a key point of this defence road, being built by NHIDCL through an EPC contractor. The 82-km, road is divided into phase-I (40-km) and phase-II (42-km). The phase-I works started on January 26and 14-km of formation cutting completed so far while boulder wall, retaining wall, gabion wall and sub-grade works are progressing satisfactorily.
After inspecting various sites, Jerang expressed satisfaction over the progress, directed NHIDCL and the contractorto make dedicated efforts by ensuring quality to complete it on time. (DIPRO)