Crores ka road useless & turned ATM! | Arun Bhumi: Why PMGSY roads defunct?

  • Sona for tailored-made PMGSY policy for hilly state

18-km Yangte-Rayang road built with over Rs 18 crore is useless now

By Pradeep Kumar

ITANAGAR, Feb 08: The Pradhan Mantri Gram Sadak Yojana (PMGSY), was launched by Union Ministry of Rural Development (MoRD) on 25.12.2000 to provide connectivity to unconnected habitations as part of a poverty reduction strategy. Thus, efforts are being made to build uniform technical and management standards high quality roads to facilitate policy development and planning at state level to ensure sustainable management of the rural roads network, according to MoRD website.

According to latest figures made available by the State Govts under a survey to identify Core Network as part of the PMGSY programme, about 1.67 lakh unconnected habitations are eligible for coverage. This involves construction of about 3.71 lakh km of roads for new connectivity and 3.68 lakh km for upgradation

Arunachal Pradesh’s total 1,479 road projects (covering 15,104-km and 267 bridges) were sanctioned under the PMGSY with 1,283 roads (13,372-km and 181 bridges) completed. Additionally, 192 new road projects (1,375-km) were approved under PMGSY-III in 2021, according to available data.  These roads links unconnected habitations in all 28 districts of this hilly state.

Takam Sonia of Arun Bhumi with documentary evidence has questioned why many PMGSY roads are inoperative? Have actions been taken against those responsible during review meetings conducted by RWD Minister Passang Dorjee Sona at Bomdila, Namsai and Itanagar? And if not why?

Showing pictures of defunct PMGSY roads in Kra-Daadi, Dibang Valley, Kurung Kumey and Shi-Yomi districts, he wondered that crores of rupees have been spent in building the roads which have become useless.

Terming these glaring examples of corruption, he asked is the way the BJP Govts led by Prime Minister Narendra Modi at the Centre and Chief Minister Pema Khandu setting examples for development?

Several videos and posts by ArunBhumi News allege corruption, misuse of funds and the use of sub-standard materials in the construction of these rural roads. There have been allegations describing some projects as “suitcase roads”—meaning they exist on paper but not in reality—or as being quickly damaged. Reports have covered issues in specific areas, including Silsango Circle (Papum Pare), where funds were allegedly misused and Metengliang area (Anjaw District), where disputes arose over compensation.

Reports indicate that roads are often left without repair after the initial maintenance period expires, with some villagers having to repair roads themselves.  The fragile terrain and high rainfall are major factors contributing to the damage, making maintenance difficult. The limited working season in the state leads to delays in project execution. There have been issues due to lack of dedicated funds for repairing flood-triggered damages to these roads. Reports highlight that numerous PMGSY roads were severely damaged by heavy rainfall and landslides.

It may be recalled here that why responding to a query raised by BJP MLA Tai Nikio during question hour in APLA on February 6, Minister Sona had said: As many as 48 PMGSY roads were damaged during last past two years due to recurrent landslides and heavy monsoon rainfall. The fragile terrain, high rainfall and geological vulnerability of the state significantly contribute to such damage, he said, adding restoration could not be undertaken for all affected roads due to the absence of dedicated maintenance funds for flood-related damage.

“Despite this, the RWD conducted emergency restoration works on ongoing projects with help of existing contractors, even though such activities were beyond the scope of the agreements,” he added.

The RWD has sought Rs 181 crore as gap funding from the state finance department for restoration of the damaged roads. “Once funds are made available, restoration works will be taken up,” he said, adding the GoAP has also approached the GoI for financial assistance to restore damaged roads, but no response has been received so far.

Responding to a supplementary question, he said the GoI had conveyed that no additional funds would be sanctioned for incomplete roads under PMGSY-I, citing that sufficient time had already been provided for execution of works.

“We are in constant touch with the GoI, requesting it to reconsider the proposal,” he said and pointed out that technological challenges and local issues have contributed to delays in PMGSY road execution, and urged MLAs to help resolve such matters at their level to avoid unnecessary delays in critical road projects.Highlighting the state’s short working season, the minister also advocated for a separate PMGSY policy tailored specifically for hilly states.

 