Sona: 1,254 of 1,309 PMGSY roads complete in Arunachal

By Special Correspondent

ITANAGAR, Mar 09: Total254 out of  1,309 roads sanctioned funder Pradhan Mantri Gram Sadak Yojana in the state have been completed, while remaining projects are yet to be finished due to various challenges, Rural Works Department Minister Pasang Dorjee Sona informed Arunachal Pradesh Legislative Assembly during ongoing budge session on Monday.

Responding to a Zero Hour discussion raised by Congress MLA Kumar Waii, Sona said the GoAP  has been prioritising construction and upgradation of rural roads to strengthen connectivity in remote and interior parts of the state.

The incomplete roads under PMGSY Phase-I are mostly located in remote and difficult areas where several constraints have affected the pace of construction, Sona said, adding that the state experiences a prolonged monsoon season, leaving a limited window for carrying out construction activities.

The Himalayan state’s rugged and mountainous terrain poses additional challenges, including landslides, heavy rainfall and other natural factors. Local issues, like land compensation disputes also delay road construction works, though compensation is not a component under the PMGSY scheme, he said.

Seeking public cooperation, Sona said roads are meant for benefit of the masses and local communities should support construction activities rather than creating hurdles.He also urged villagers to monitor road construction works in their respective areas to ensure transparency and quality.

Sona further said the Centre has declined to extend deadline for completion of unfinished roads under PMGSY Phase-I. However, the GoAP has requested the Centre to allow an extension till March next year to enable completion of the remaining works.

He added that the state government has also submitted a proposal to the Centre seeking relaxation of the population criteria under PMGSY so that more habitations in the state can be connected with all-weather roads.

Apart from the centrally sponsored scheme, the GoAP is also undertaking additional road construction works under the state plan to bridge connectivity gaps in areas not covered under the programme.

Road projects being implemented are under the Chief Minister’s Comprehensive State Rural Development Programme (CMCSRDP) as a stop-gap arrangement to improve rural connectivity.

Launched by the Centre, PMGSY aims to provide all-weather road connectivity to eligible unconnected habitations.

In Arunachal Pradesh, the programme has played a key role in linking remote villages with district headquarters and improving access to essential services such as healthcare, education and markets.

Highlighting another issue, hesaid the use of nanotechnology in road construction introduced by the Border Roads Organisation has not been successful in the state due to its unique terrain and climatic conditions.“The matter has been raised with the GoI at various levels,” Soan said, adding that no positive response has been received so far.