By Special Corresondent
ITANAGAR, May 13: The state Govt following sustained pressure from activists and East Kameng Social Welfare and Cultural Organisation (EKSWCO) has reportedly issued a recovery order worth ₹114 crore in Lada-Sarli stretch of Arunachal Frontier Highway land compensation scam.
The Land Department confirmed the file has been forwarded to chief secretary for approval. Officials, however, did not disclose the exact amount marked for recovery.
The Lada-Sarli stretch, part of the AFHunder Packages 1–5 covering a 125–126-km stretch in East Kameng and Kurung Kumey districts, has been mired in compensation irregularities allegedly worth ₹100–130 crore.
The Ministry of Road Transport and Highways had sanctioned ₹241 crore, including administrative costs, for land compensation on this stretch. Of this, ₹224 crore was released. Reports suggest over ₹100 crore was disbursed against bogus claims, inflated asset valuations and fake beneficiaries.
The Anti-Corruption Bureau (ACB) had arrested former East Kameng DLRSO Takam Kechak and others. At least 4–5 officials were suspended. Brokers accused of facilitating bribes were also detained. Assets worth ₹9 crore have been frozen and recovered so far, while ACB investigations are ongoing.
Recently, the project stretch was transferred to the Border Roads Organisation (BRO) amid poor response in re-tendering, concerns over contractor concentration and delays in compensation disbursal.
The construction timeline is set at 3 years with 5 years of maintenance, but progress remains slow due to fallout from the scam.
The ambitious AFH (NH-913), also known as Bomdila-Vijaynagar Highway, is a massive 1,748-km strategic infrastructure project, stretching from near Bhutan in the west to the Myanmar border in the east.
Running near India-China border (LAC), this project aims to improve defense mobility and boost economic development in remote areas, with target completion around 2027-28.
This 2-lane hard shoulders and 5.5-meter intermediate lanes, featuring a significant 800-km greenfield section, tunnels and bridges would connect, Bomdila, Nafra, Huri, Mechuka, Tuting, Hunli, Hayuliang, Hawai, Miao and Vijaynagar.
The AFH in April last was entrusted to the Border Roads Organisation (BRO) and the National Highways and Infrastructure Development Corporation Limited (NHIDCL), taking over from the state PWD.
The project faces challenges from terrain, potential land compensation issues and investigations into land scam allegations in specific stretch like Lada-Sarli.
Construction is ongoing, with some sections completed, such as portions of Hunli-Anini road and Hayuliang–Hawai road, according to NHIDCL reports.
On completion, it qould enhance national security through all-weather connectivity, supports the Vibrant Villages Programme and connects border areas to the mainland.
While planning of 1,840-km AHF (NH-913) project began in 2016-2018 with initial survey works conducted, major construction packages were approved in 2023-2024. The works was launched by Prime Minister Narendra Modi on 22.09.25 with a completion target by 2027–2028.