By Pradeep Kumar
ITANAGAR, May 30:Arunachal Pradesh, known as nature’s trove, blessed with 58,800-MW hydropower potential, is fast minting its liquid gold, if the records are any indication.
The National Hydro-Electric Power Corporation Limited (NHPC) operationalized its 4th unit of its underexecution 2000-MW Subansiri Lower Hydroelectric Project (SLHP) on May 8 last. The remaining five 250-MW units are scheduled to undergo dry/wet testing for commissioning in phases during 2026-2027.
The SLHP (inpicture) on being commisioned would support grid stability, meet peak power demand and assist integration of renewable energy into the national grid while enriching stae coffer.
In a landmark development for India’s renewable energy sector and Arunachal Pradesh’s hydropower ambitions, the GoAP on May 27 signed a MoA with M/s Greenko Demwe Power Limited, formerly Athena Demwe Power Limited, for execution of 1750-MW Demwe Lower Hydroelectric Project (DLHP) on a build, own, operate and transfer (BOOT) basis.
The MoU of the mega hydropower project marks one of the largest hydropower collaborations undertaken with a private sector developer reinforces the state’s strategic role in India’s clean energy transition.
The project forms part of the GoI’s ambitious 50,000 MW hydroelectric initiative aimed at expanding country’s renewable energy capacity. Arunachal Pradesh, endowed with immense hydropower potential, continues to play a crucial role in achieving the nation’s long term clean energy goals.
The DLHP, proposed on Lohit River, will have an installed capacity of 1750-MW comprising five generating units of 342 -MW each along with one unit of 40-MW. The project is expected to generate approximately 7326 million units of electricity annually in a 90% dependable year at 95% plant availability, thereby making a substantial contribution to India’s energy security and renewable energy generation.
The project site is located in Lohit district near Parasuram Kund/Brahma Kund and enjoys strategic connectivity through Dibrugarh Airport, Tinsukia railhead and road access from Parasuram Kund. It has been designed as a major engineering and infrastructure initiative with a concrete gravity dam having a maximum height of 163.12 metres above deepest foundation and a total crest length of 474.35 metres.
The reservoir at full reservoir level will have a storage capacity of 516.38 million cubic metres with a water spread area of approximately 1131 hectares. The project design includes a modern spillway system comprising surface ogee and sluice spillways with multiple gates to safely handle flood discharge.
It would feature an advanced hydropower infrastructure system including six diversion tunnels, underground pressure shafts, and a large surface powerhouse located on the right bank of the river. The powerhouse has been designed with vertical Francis Turbines operating at a design head of 112 metres and a design discharge of 1729 cumecs.
Apart from strengthening India’s renewable energy capacity, the project is expected to provide major socio-economic benefits to the sate through employment generation, infrastructure development, improved connectivity and increased economic activity in the region. Large scale direct and indirect employment opportunities are expected during both construction and operational phases.
The signing of the MoA reflected growing investor confidence in the state as a premier destination for clean energy and infrastructure investment. The GoAP expressed confidence that the DLHP woould emerge as one of the flagship hydropower projects in the India and a defining milestone of state’s development journey.
This Himalayan state boasts of approximately 40% of India’s total hydropower potential. While the state’s present installed operational capacity is around 800 MW, a massive 19-GWof HEPs under development with an investment outlay of over ₹2 lakh crore.. The state expects to eventually generate over ₹4,500 crore annually from free power once the mega projects are fully realized. Its current annual revenue from operational hydropower projects is roughly ₹500 crore. The state has declared 2025–2035 as the “Decade of Hydropower” and undergoing a massive hydropower boom. Once ongoing mega-projects are fully operational, the state expects to receive roughly ₹4,525 crore annually from the sale of its share of free power.
This coincides with the view of Chief Minister Pema Khandu that hydropower is state’s main economic driver. The upcoming projects are expected to generate over ₹4,000 crore annually in free power for the state exchequer, along with an additional Rs 1,884 crore in annual dividends and significant community development funds. i.e., ₹5,884 crore annually.
Deputy Chief Minister Chowna Mein presented a ₹36,607 crore state budget for 2026–27 financial year, featuring a ₹701.43 crore deficit. The budget is heavily focused on six key pillars: infrastructure development, people-centric development, economic growth, employment generation, fiscal stability, and governance reforms.
It calculated state earning of ₹35,905.57 and reflected ₹701.43 crore. If the earning swelled by ₹5,884 crore annually, it would be a surplus budget. The state from a fund-poor would become a fund-ruch state to ensure development the way the GoAP decides tomeet people’s expectations.