ITANAGAR, Oct 01: The 2,000-MW Subansiri Lower Hydroelectric Project in Arunachal Pradesh has achieved a key milestone with the completion of a major electro-mechanical work, officials said on Thursday.
The successful “lowering of the 395-metric tonne generator stator of unit 7” takes the project a step closer to completing its full installed capacity, they said.
The electro-mechanical work was completed on Wednesday, marking another important stage in the construction and commissioning of the project, which comprises eight generating units of 250 MW each, the officials said.
Deputy Chief Minister Chowna Mein, who also holds the Power and Hydropower portfolios, shared the development in a social media post on Thursday.
“This critical milestone in the electro-mechanical works brings the project closer to commissioning unit 7 and, subsequently, its full installed capacity of 2,000 MW (8×250 MW),” Mein said in a post on X.
The project, being developed by the NHPC on the Subansiri River along the Arunachal Pradesh-Assam border, is designed to generate around 7,422 million units of electricity annually once fully operational.
Two of its units had been commissioned by March this year, while the NHPC subsequently declared the third unit commercially operational from March 20, taking the commissioned capacity to 750 MW.
The Union power ministry had earlier indicated that the entire project was scheduled for completion by December. PTI