By Special Correspondent
ITANAGAR, Oct 10: The Public Works Department (PWD) has assured that ongoing pothole filling and patch repair works of Itanagar–Banderdewa stretch of NH-415 (Package-B) will be completed within two weeks from October 8.
In a press statement issued on Saturday, Chief Engineer (Highways) appealed to the organisers to withdraw the proposed October 13 protest rally, assuring that repair works are being carried out on a priority basis.
The PWD (H) revealed that the original four-lanning contract was terminated on 29.04.26, due to unsatisfactory performance with only 51.37% of the project completed.
A revised proposal worth ₹303.64 crore for remaining works has been submitted to Union Ministry of Road Transport and Highways and its approval is awaited.
However, around 7,000 square metres of road repairs have been completed against targeted 21,000 square metres under the maintenance contract. Thus, the CE sought public cooperation to ensure uninterrupted repair works and early restoration of the highway.
The protest rally has been proposed on October 13 resenting the dilapidated condition of the NH, the lifeline of Capital Complex, and seeking its immediate repair.