- Mein seeks early sanction
SHILLONG, Sept 25: Union MoRTH, Shipping & Water Resources Minister Nitin Gadkari reviewed statge-wise National Highway projects implemented in eight North Eastern states durin g last two days that covered land acquisition, forest clearance, muck dumping and other issues related with the project implementations and progress of works.
While reviewing all NH projects implemented in Arunachal Pradesh, Gadkari said that the MoRTH wants to execute road and highways projects rapidly in the state to bring road connectivity to remote places, accelerate economic development and generation for the people. However, he said that execution of many important projects are getting inordinately delayed due to the state’s own problems regarding land acquisitions, forest clearance and other issues, causing huge losses and embarrassment to his ministry.
He asked the GoAP to fast track the land acquisition, forest clearance and other issues, saying that the MoRTH will not take time to sanction fund for projects free from any encumbrance. Once NH projects are successfully implemented would be notified as National Highways, he annouonced.
He asked the contractors to improve their performance and expedite progress as per stipulated time by increasing their manpower and machineries and cautioned that the non-performing contractors would be terminated and banned from contesting in any tender, if requires.
Deputy Chief Minister Chowna Mein while presenting the status of state’s NH projects, submitted a memorandum to Gadkari seeking early sanctioning of 407-km Potin-Pangin Road (NH-13), including fund for repair & maintenance of four major bridges, 35-km Hukanjuri-Khonsa road, remaining 20.6-km (package B & C) of 4-laning of Itanagar-Banderdewa road (NH-415).
He called for early sanctioning of balance work of Lalpul-Manmao-Changlang and Longding-Tissa-Khonsa roads, whose contract works were terminated earlier due to non-performance of the contractors. He sought sanction of remaining Rs 103.99 crore fund out of Rs 113 crore required for permanent restoration works damaged by landslides and floods during 2017-18. The MoRTH has so far allotted Rs 9.01 crore only for temporary restoration, Mein said.
He also sought an additional Rs. 45.71 crore required for restoration of flood damages occurred during current financial year up to August 2018-19 and allotment of Rs. 200 crore during current fiscal for FDR & maintenance work.
He requested Gadkari to formally declare four existing state roads – 120-km Akajan–Likabali–Bame, 44-km Margherita–Changlang, 125-km Daporijo-Gerukamukh road (Dumporijo) to Geruka Mukh (Assam/Dullangmukh)-Gogamukh at Dhemaji district in Assam under green field alignment and 59-km Tezu–Chapakhawa road via Sunpara, all approve earlier as NHs in principle.
The state has total of 72 packages with total length of 2537-km under NHs with estimated cost of Rs 25,000 crore being executed by agencies like state PWD, MoRTH (BOT), BRO and NHIDCL.
The proposed problems of executing agencies and contractors of Arunachal Frontier Highway were also discussed.
Gadkari, before the meeting, has dedicated upgraded and renovated 2-lane Jowai-Ratacherra road in Meghalaya to the people.
Besides the chief ministers, DyCMs and PWD ministers of NE states, heads of executing agencies and contractors were also present. Mein was accompanied by PWD commissioner Bilatee Pertin and CE (Highway) Toli Basar. (PRO)