GERUKAMUKH, Aug 16: The construction of 2000-MW Subansiri Lower Hydroelectric Project (SLHEP) will resume after rainy season as all legal hurdles have been cleared, its executive director Arvind Bhat said, in his address to 73rd Independence Day celebration here on Thursday.
The NHPC is committed to complete the project with support of local people of Arunachal Pradesh and Assam who always have been receiving our patronage. It would yield development not only in the area but both states will get their share of electricity too, he said, adding the country will develop faster if all stand united to work.
The project has provision for flood moderation during monsoon season for which protection works along both banks of Subansiri River upto 30 km downstream have been undertaken to control flood and checking soil erosion, he said.
NHPC employees with their family members, KV students and large number of people from nearby areas witnessed the celebration. A friendly cricket match between eleven and GM eleven was organized later and the players braving intermittent rain exhibited their sportsmanship spirit to the applause of the spectators, according to an NHPC release.
AONS adds: The SLHEP halted since December 2011 after completion of almost 60% works has been incurring a daily loss of Rs 10 crore but on completion it will be largest project of India.
The Supreme Court in March last had set aside an order of the National Green Tribunal giving a go ahead to the SLHEP, which was conceived as the country’s largest hydroelectric project planned by the NHPC on Assam-Arunachal Pradesh border and called for a review of recommendation made by the expert committee in this regard.