JULLANG, Sept 14: Papum Pare DC Cheechung Chukhu asked authorities of the CPWD and Satyajit Ray Film and Television Institute (SRTFI), Kolkota to be empathetic towards the land donors, who have donated 43.32 acres of land free of cost for the construction of the institute.
He said this While chairing a joint meeting of the district administration (DA), information and public relations department, PRI members, GBs, land donors of Film and Television Institute (FTI) at Jote (Jullang Rakap) and representatives from CPWD to assess land dispute and water supply connection issues of FTI here on Thursday.
Addressing the CPWD and SRTFI members, he specifically pointed out that “In many parts of Arunachal Pradesh, including Papum Pare district, natural resources like water, forest etc have private/community ownership. So individual/ community consent becomes indispensable to execute the works smoothly.”
“This joint meeting is the result of lackadaisical attitude of the CPWD and SRTFI towards the land donors and their grievances. For any developmental work of such a big stature to be completed successfully on schedule, building rapport and winning the confidence of the local is a prerequisite,” he said.
“Out of the 43.32 acres only 3 acres is disputed, which can be resolved through proper coordination among the executing agencies, FTI and stakeholders like land owners and PRI leaders,” he said, and urged the land owners to coordinate with the DA.
IPR director Onyok Pertin said that the “Role of the IPR department in the project is supervisory and monitory in nature. The department acts as bridge between the land donors, SRTFI and the Govt”.
He suggested drafting a memorandum of agreement between the FTI and the land donors to ensure recognition of the sacrifice of the donors.
Rakap GPC Taba Kunya, on behalf of land donors, said that the “public of Jullang Rakap have cooperated with the CPWD and have made no claims on any civil work so far”.
“However, the water supply work, for which the survey was conducted by the PH&WSE department with the assistance of the PRI members and GBs of Jullang Rakap village should involve PRI members for execution,” he demanded.
Kunya also felt that “Few considerations should be made for group C and D posts for the land donors once the FTI becomes functional.”
After threadbare discussions, the owners of the 3 acre disputed land agreed to withdraw their cases in lieu of some lump sum compensation; a representation to be submitted to Union Ministry of Information and Broadcasting (MoIB) to involve the PRI leaders, GBs and public during water supply work execution and posting of SRTFI officials and officers who would understand local sentiments.
The FTI is an ambitious project of the MoIB whose foundation stone was laid on February 9, 2019 by Prime Minister Narendra Modi. The FTI is the first FTI in the North East region and third in the country.
IPR deputy director Marbang Ezing, Sangdupota CO Dr. Heera Panggen, Sangdupota ZPM Hina Camdir Tok, GBs, land donors and CPWD engineers were present. (DIPRO)